Facilities Revitalization Project
Update – Jan 20, 2015
The last few major tasks were tackled over the winter break. The last bits of the old office space including filing cabinets, lockers and fridge were moved into the storage space adjacent to the gym. The last of the carpeting was put in place and we are now enjoying the vastly improved usability of the gym.
There are still a number of important jobs that we’d like to complete prior to hosting the Judges Cup, Feb 14
If you’re interested in getting involved, contact Steve (steve@glaciergymnastics.com), or add your name to the list and receive emails whenever something is being planned.
Current Task List
- Installation of final high bar on wall
- Framing to attach foam padding in high risk areas (pillar and stairway by beams / stairway to office / wall by trampolines)
Pictures of the project…
Thank you to our major sponsors thus far…
Purcell TimberFrames | Kalesnikoff Lumber Co. | Home Hardware – Nelson | A & A Painting |
Estimated Project Timeline
The following schedule is the best estimate of when the different tasks will be happening. Contact Steve to get involved. Mail Steve ph: 352-2227
Jun 16 | Equipment Take Down (part of Year End Show set up) |
6 people + coaches | 2 hours |
Jun 16-19 | Mezzanine Prep (ledger install, etc) |
crew of 4-6 volunteer – skilled carpentry |
4-8 hours |
Jun 23-25 | Timber Frame Install (Purcell TimberFrames) | 2-3 strong volunteers | 1-2 days |
Jun 23-24 | Dismantle Spring Floor (multiple crews) |
8-12 hrs / 4-10 people | 1-2 days |
Jun 24-25 | Remove rest of equipment | 2-3 people and coaches | 4 hours |
Jun 23-25 | Replace Fluorescent Lights (start as soon as lift is delivered) |
crews of 2 | 8-12 hours |
Jun 30 | Painting to start | multiple crews | 1-2 weeks |
Jun 26-Jul 6 | Mezzanine Framing & Finishing | skilled trades | 1-2 weeks |
Jun 30+ | Reinstall Spring Floor | big job; crew of 10 | 2 days |
Framing around Floor (once floor is installed) |
crew of 3-6 volunteer – skilled carpentry |
1 day | |
Jul 2 | Prepare for Camps Start Setup Gymnasium: (beams area, tramps) |
crews of 1-3 o + coaches | 1-2 days |
Jul 28-Aug 13 | Misc equipment setup: (Bars, Beam, Flooring, Rings) |
smaller crews of 1-2 | 1-2 days |
1st 2 weeks in August | Office Move -prepare for Fall (mezzanine complete; electrical, etc) |
crews of 4-6; heavy lifting | 1-2 days |
Wednesday, Feb 19th: Late Night Demo Success!!
A great deal was accomplished in about 3 hours of work and almost 1/3 of the area demo completed. The next one is planned for…
Wednesday, Feb 26th – 9:00 – midnight
Sign Up Here if you can help – we need 5-6 people.
If you’re interested in contributing to the club in a way that will have positive benefits for years to come, please consider becoming involved. We have many volunteer opportunities available especially with the required demolition work.
Add Your Name to the Contact List
Next Steps…
- completing the demo in 2-3 work sessions (volunteers required)
- build and install mezzanine offices (tentatively sometime around spring break)
- move the offices (one weekend or evening after the build)
- gym layout changes – explore pit development (summer 2014)
- facility development / equipment purchase2014-2015 season
Hope to see you down on the gym floor with tool belts, tape measures and brooms!
Completed! – Site Preparation
Wednesday, Feb 19th: A skilled crew of 6 demoed about 1/3 of the mezzanine in a 3 hour late night effort!
Sunday October 6th: A work crew of about a dozen people volunteered over 60 hours to clean out old storage space and prepare it for better use. The mezzanine area was prepped for demo.
Thank-you, to all of the GGC members who came out to help with the clean up! 50 years of dusty, long forgotten storage is no longer cluttering the west end of the gym.